Start-Up
At the end of configuration, the FPGA automatically pulses
the Global Set/Reset (GSR) signal, placing all flip-flops in a
known state. After configuration completes, the FPGA
switches over to the user application loaded into the FPGA.
The sequence and timing of how the FPGA switches over is
programmable as is the clock source controlling the
sequence.
The default start-up sequence appears in
Figure 68, where
the Global Three-State signal (GTS) is released one clock
cycle after DONE goes High. This sequence allows the
DONE signal to enable or disable any external logic used
during configuration before the user application in the FPGA
starts driving output signals. One clock cycle later, the
Global Write Enable (GWE) signal is released. This allows
signals to propagate within the FPGA before any clocked
storage elements such as flip-flops and block ROM are
enabled.
The function of the dual-purpose I/O pins
, such as M[2:0],
VS[2:0], HSWAP, and A[23:0]
, also changes when the
DONE pin goes High. When DONE is High, these pins
become user I/Os. Like all user-I/O pins, GTS controls when
the dual-purpose pins can drive out.
The relative timing of configuration events is programmed
via the Bitstream Generator (BitGen) options in the Xilinx
development software. For example, the GTS and GWE
events can be programmed to wait for all the DONE pins to
High on all the devices in a multiple-FPGA daisy-chain,
forcing the FPGAs to start synchronously. Similarly, the
start-up sequence can be paused at any stage, waiting for
selected DCMs to lock to their respective input clock
By default, the start-up sequence is synchronized to CCLK.
Alternatively, the start-up sequence can be synchronized to
a user-specified clock from within the FPGA application
using the STARTUP_SPARTAN3E library primitive and by
setting the StartupClk bitstream generator option. The
FPGA application can optionally assert the GSR and GTS
signals via the STARTUP_SPARTAN3E primitive. For JTAG
configuration, the start-up sequence can be synchronized
to the TCK clock input.
X-Ref Target - Figure 68
Figure 68: Default Start-Up Sequence
Start-Up Clock
Default Cycles
Sync-to-DONE
01
2
3
4
5
6
7
01
DONE High
23
4
5
6
7
Phase
Start-Up Clock
Phase
DONE
GTS
GWE
DONE
GTS
GWE
DS312-2_60_022305